Maintenance (REMIT)

The information on this webpage is for general information purposes only 
 
The maintenance events that are disclosed on this page are those that may have the potential to significantly effect the prices of certain "wholesale energy products".

Unplanned Events

Planned FPS maintenance (updated 4 September 2017)

2017

Change-over to new LPG refrigeration unit, expected to complete 21 October.  No LPG export until then.

2018

MOL ESDV test at Cruden Bay for 1 day on the 1st/2nd August (tbc). FPS will fully shut in for the duration of the test.

Unity ESDV test for 1-3 days on 1st/2nd August.  All Unity entrants will be shut down.

Annual ESDV test on Forties Charlie for 1 day on the 1st/2nd August.   All Forties Charlie entrants will be shut down.

Six monthly (April, August) GAEL Shutdown to enable pig retrieval.  All GAEL entrants will be shut down.

TR2 TAR.  Part 2 : 9 weeks (May).  Impact on throughput subject to actual shipper demand.

Disclaimer

The information contained on this website may not be comprehensive. Despite our efforts, it may not be accurate, up to date or applicable to the circumstances of any particular case. We cannot accept any liability for any inaccuracies or omissions in this websiteand any decisions you make based on information contained in this website are your sole responsibility.

In addition we cannot accept liability in respect of any interruption, defect, delay in operation or transmission, loss of data, communication or line failure or failure of security controls in relation to the website, or unauthorised access to, or alteration of or use of the website or the disclosures contained herein by any other party.