The art of well planning

Illustration of seismic imagery on gallery wall
Knowing how to locate and design wells reaching down into subsurface reservoirs can be a tricky business. But thanks to a sophisticated planning tool developed by BP, the company's well planners are finding more effective ways to optimise well designs. Mike Moss reports
Bringing together previously isolated activities can sometimes yield a far more beneficial result than was expected - a synergistic effect, often encapsulated in the phrase 'the whole exceeds the sum of the parts.'

Such was the case in the early development of BP's well planning toolkit (WPTK), which was born out of necessity in 2000 after BP had made a number of significantly large oil discoveries in the deep waters of the Gulf of Mexico. Reaching these prizes, the largest of which was the Thunder Horse field with reservoirs lying some 5500m to 8000m below the seabed, required a number of deep appraisal and development wells to be drilled through complex subsurface geology, compounded by the deep water above. In short, a way had to be found to achieve extraordinary performance while working at the technical limits of drilling at that time.

BP's approach to the challenge brought drilling information and a comprehensive description of the subsurface together for the first time. The move was to initiate a step change in the level of cross-functional interaction in well planning, one which has gone on to deliver many positive business impacts for BP - for example, a decade later Thunder Horse has become the most productive deepwater field in the world (see feature 'Deepwater horse power', this issue).

Faced with the unusual subsurface challenge, BP petroleum systems analyst Stephan Duppenbecker, working in co-operation with earth modelling specialist Jean-Sebastian Hall and team colleague Amal Vittachi, set about developing a 'toolkit' which brought together several aspects of well planning that had previously been considered separately in isolation.

Detailed 3D models of the subsurface can be studied in BP's HIVEs, enabling proposed well trajectories to be viewed
Detailed 3D models of the subsurface can be studied in BP's HIVEs, enabling proposed well trajectories to be viewed
One particular conundrum facing the subsurface team was how to drill wells in a very uncertain environment of pore pressure and fracture gradient. Pore pressure is the pressure exerted by the fluids held in the penetrated rocks, and these fluids must be prevented from entering the wellbore during drilling by the higher pressure of the circulating 'drilling mud' fluids; while fracture gradient is the point at which the rock structure would begin to break down if the drilling mud pressure is too high. Working in the window between the two pressures is necessary to drill a successful well - but for the subsurface geology in question, the window was narrower than usual, and it varied with increasing depth.

Duppenbecker and his colleagues brought together two normally separate sets of data in the creation of the embryonic WPTK - 3D basin modelling, a geological process which mimics sedimentary layering of the subsurface over time, and pore pressure prediction, based on velocity analysis from seismic data. Although levels of correlation between the two were by no means universally consistent, the combination of two sources of data into a single output became the enabler for more accurate predictions of pore pressure and fracture gradient.

But the integration extended beyond the data itself. The ability to visualise the particular properties of a proposed well in three dimensions - and particularly in BP's advanced HIVE (highly immersive visualisation environment) - helped to bring members of the subsurface and drilling teams together to collaborate on common ground. For example, it enabled the drillers to view pore pressure data along the proposed well path, as well as the geological context of the data.

'The WPTK helped to increase confidence levels within the drilling community,' explains Duppenbecker, 'particularly as our pore pressure predictions improved. We could discuss the risks and uncertainties together, we could influence the cost of the wells, and our drilling record became better and better as a result.'

Fast forward over the 10 years between then and now, and the WPTK software has grown both in functionality and in its application. Whether running on a laptop computer or seen at its best on the 'big screen' when viewed through 3D spectacles in a HIVE, the toolkit is giving BP's subsurface teams an advantage in designing, viewing and modifying wells.

'The net result is shorter well planning cycle times and improved cross-functional interaction between subsurface and drilling teams - leading to significantly reduced risks and costs in drilling wells,' observes Nigel Last, senior drilling advisor within BP's exploration and production technology group at Sunbury.

Graphic about the shared earth model
Graphic about the shared earth model
'As an advanced well planning and visualisation tool, WPTK provides BP with the ability to address complex well issues and development scenarios in a more effective way by integrating data from different disciplines or applications - skills which were once pursued in isolation are all connected up now. For example, the toolkit enables wellbore stability and pore pressure calculations to be carried out, at the same time taking into account other parameters such as the ability to drill around faults.'

Defining the subsurface is achieved in a 'shared earth model', which is a continually growing database of rock strength and stress data gathered by BP's subsurface teams around the globe. By linking this data with the software algorithms in the WPTK, wells can be defined either singly or in multiples almost at the proverbial 'touch of a button'.

'In essence,' adds Last, 'we define the characteristics of the subsurface we have to drill through, and WPTK then carries out the design calculations for the wells.'

Toolkit in action

One field development to benefit from WPTK is the BP-operated Clair field, located in 140m of water to the west of Shetland in UK waters. Despite the prize of an estimated five billion barrels of oil in place, Clair remained on the 'too risky to develop' list between its discovery in 1977 and approval of the first phase of development in 2001.

When production commenced in 2005, that first phase development encompassed a relatively small area of the overall reserves, accessed from a single offshore platform. While early near-vertical wells drilled into the reservoir below the platform proved relatively straightforward, the level of challenge rose sharply as both the distance and angle from the vertical increased on wells needed to reach the more distant hydrocarbon targets.

'The BP team needed to find a way to calculate, within a relatively narrow band, the weight of the drilling mud required to drill and stabilise the wellbore,' explains structural geologist David Barr. 'Too low in weight and the wellbore would collapse, too high and the weak rock formations could fracture.'

This proved to be a huge challenge as the early wells showed that Clair did not display the rock behaviour predicated by conventional analysis. A dedicated investigation team identified an unusual condition known as weak-plane failure as the likely cause, and began the laborious process of calculating the critical points along the proposed route of a well aimed at part of the reservoir some four kilometres from the platform.

The well was a success, and the weak-plane model has since been implemented in the WPTK where it now allows accurate mud weight calculations to be carried out quickly and easily.

'The arrival of the WPTK implementation enabled us to transform what had been a slow process covering one well at a time, into the continuous processing of multiple wells,' adds Barr. 'The principal way in which the WPTK has come into its own on Clair is not so much for the calculations it enables for the individual wells - although that's nice to have, it is achievable by other means - it's more for the ability to efficiently and interactively plan multiple wells, for example when choosing between alternative platform locations for the next stage in field development.'

Clair is by no means the only development to seize the potential within the WPTK to compress the time required for well planning and to enable human resources to stretch further.

Graphic about the well planning tool kit
Graphic about the well planning tool kit
A case in point is in BP's Azerbaijan business unit where the WPTK has been credited with reducing the cycle time for well planning and delivery from three man-years to one, with consequent savings in costs and manpower for wells drilled in the Caspian Sea - the toolkit has also been applied retrospectively to examine existing wells in the Azeri-Chirag-Gunashli development operated by BP, and for the development of the Shah Deniz field, also in the Caspian. In Egypt, the WPTK has been deployed successfully in prospect evaluation by BP, and also in Indonesia for the Tangguh development.

Challenging compaction

Another example of how the WPTK can help to optimise the development of very challenging prospects lies in BP's Valhall field, an over-pressured Upper Cretaceous chalk reservoir in the North Sea some 290 kilometres off the southern coast of Norway. The field has been under continuous development since it came onstream in 1982 and currently has 52 producing wells supported by a complex of platforms - further development work now under way should see Valhall continue to produce until around 2050.

One significant characteristic of Valhall's reservoir is compaction of the chalk formation - compaction in excess of 10m has occurred in places. Another is seabed subsidence, exceeding six metres in some areas of the field.

'Valhall has become more and more difficult to drill over time,' explains Tron Golder Kristiansen, geomechanics advisor in BP Norway. 'Our challenge now is to predict the spatial and temporal impact of the compaction and subsidence to find the low risk well trajectories during the remainder of the field's life.'

Graphic about well planning in action
Graphic about well planning in action
A finite element model was produced to compute all the deformation and stresses that had taken place in the subsurface over 25 years of production. This was then fed into the WPTK to predict wellbore stability and optimum mud weights for future well designs.

The results were first applied to a well which runs from the central water injection platform to Valhall's northern basin, sending water into the reservoir to provide pressure support for the producing wells in that area. The wellbore stability calculation performed by the WPTK flagged up an exceptionally narrow window between the minimum weight of mud needed to avoid wellbore collapse and the maximum weight at which mud circulation would be lost into the formation. As a result, a modified trajectory was selected for the well, which was drilled successfully 61 days ahead of schedule, bringing multi-million dollar cost savings compared to the original drilling budget.

The WPTK has now become a standard method for checking projected well paths before drilling at Valhall, delivering significant savings.

Live well planning

The combination of the WPTK and its associated shared earth model is set to become increasingly valuable as complex oil and gas reservoirs are encountered in the future.

'People didn't need to worry too much about rock mechanics 20 or 30 years ago when the oil fields were in accessible and well understood places,' says Last. 'But the industry is moving into new areas where the way rock behaves is more uncertain. Fortunately, BP now has the WPTK to enable us to model complex wells and visualise them in three dimensions, while the shared earth model has become the place where all the mechanical properties of the rock formations are stored in a standardised format. This will be useful to the reservoir engineers who manage the field during operations once the drilling campaign has been completed.'

Much of the focus behind the development of the toolkit, which is now being taken forward by Randy Hickman and Steve Willson in BP Houston, has been to achieve cost savings throughout BP's global drilling programme by eliminating 'drilling surprises' and reducing non-productive time. Progress towards both these targets stands to receive significant impetus if it proves possible to link the WPTK to real-time data acquired as a well is actively being drilled - BP's first offshore trial is likely to take place soon. This link, an advance on conventional measurement-while-drilling (MWD) techniques, will enable pre-drilling models to be checked and updated using real-time data from the well, which in turn would provide early warning of the need to change drilling parameters should the data not match expectations.

A key enabling technology for this next step is the recent development of wired drill pipe, which will send a data stream from the drill bit at speeds measured in megabits per second, rather than the relatively leisurely four bits per second currently available using conventional mud pulse telemetry for MWD. This real-time link, says Last, will help to take BP's WPTK even closer to that 'drilling Nirvana' of being able to 'see' a well as it is being drilled, and to react to challenges in real time.

With WPTK now firmly established, BP is truly benefitting from the synergy of the whole being greater than the sum of the parts.