Installation in 2000 meters water depth, a first for India

On 26th December, we completed the as planned mobilization of the DLV2000 on Reliance R / S Cluster 8 well OBO development project in Bay of Bengal, East Coast India for season 1 offshore campaign. 

The DLV2000 will install the first 30 km of 56 km piggy back 18-inch x 4-inch export / vent pipeline in water depth up to 1,200 m(balance of 56 km piggyback pipeline, from 1,200 m to 2,000m water depth and J-PLET will be installed by Allseas Audacia) , 43 km 6-inch MEG pipelines, 90 ton SSIV piping module, UDH and DWPLEM foundation piles, and 100 m piggyback 18-inch x 4-inch riser on existing live platform.