Angelin

Angelin will become BPTT’s 15th offshore production facility. The facility will be located 60 kilometres off the south-east coast of Trinidad in water-depth of approximately 65 metres. Angelin was originally discovered by the El Diablo well in 1995 and appraised by La Novia in 2006.

The development will include four wells and will have a production capacity of approximately 600 million standard cubic feet a day (mmscfd). Gas from Angelin will flow to the Serrette platform hub via a new 21 kilometer pipeline.

Drilling is due to commence in Q3 2018 and first gas from the facility is expected in 1Q 2019.