BP Exploration (Caspian Sea) Limited is the operator on behalf of the Contractor Parties to the ACG Production Sharing Agreement.
In the first quarter of 2026, bp and its co-venturers spent about $134 million in operating expenditure and about $363 million in capital expenditure on ACG activities.
During the quarter, the 4D high-definition ocean bottom node seismic programme on ACG progressed with processing of the data acquired in 2025.
Offshore operations as part of the multi-well subsea intervention campaign in the Deepwater Gunashli area also continued. The first subsea intervention job within the campaign has now been successfully completed, and the data gathered enabled the well to safely return to injection service.
Production
During the quarter, ACG continued to safely and reliably deliver stable production. Total ACG production for the quarter was on average about 325,000 barrels per day (b/d) (about 29 million barrels or 4 million tonnes in total) from the Chirag (19,500 b/d), Central Azeri (89,800 b/d), West Azeri (74,800 b/d), East Azeri (43,900 b/d), Deepwater Gunashli (47,700 b/d), West Chirag (22,600 b/d) and ACE (26,700 b/d) platforms.
At the end of the first quarter, 149 oil wells were producing, while 50 were used for water and 11 for gas injection.
Drilling and completion
In the first quarter of 2026, ACG drilled and completed two oil producer, three water injector and one gas injector wells.
Associated gas
During the quarter, ACG delivered an average of around 12 million cubic metres per day of ACG associated gas to the state of Azerbaijan (1 billion cubic metres in total), primarily at the Sangachal terminal but also to SOCAR’s Oil Rocks facility. The remainder of the associated gas produced was re-injected for reservoir pressure maintenance.
Non-associated gas (NAG)
Following the signing of the ACG NAG Addendum in 2024, an initial production well was planned and safely drilled from ACG’s existing West Chirag platform. The well also represents a significant appraisal milestone, as the data obtained will help build future plans for ACG’s NAG development.
The well was successfully delivered in 2025, providing access to two priority NAG deep reservoirs - the shallower Qirmaki Upper Sand and the deeper Qirmaki Lower Sand reservoirs - both located beneath the currently producing oil reservoirs.
The well confirmed presence of gas resources in the shallower Qirmaki Upper Sand reservoir, which is the main target reservoir for first NAG production.
Additionally, the well encountered high pressure gas in the deeper Qirmaki Lower Sand reservoir from which first NAG production is planned to commence in the first half of the year as part of an initial period of well and reservoir testing, alongside production.
Production will then move via a well recompletion to the shallower Qirmaki Upper Sand reservoir – the main target reservoir for sustained production - in the second half of the year.
In the first quarter of 2026, oil and gas from ACG and Shah Deniz continued to flow via subsea pipelines to the Sangachal terminal.
The daily capacity of the terminal’s processing systems is currently 1.2 million barrels of crude oil and condensate, and about 81 million standard cubic metres of Shah Deniz gas, while overall processing and export capacity for gas, including ACG associated gas is around 100 million standard cubic metres per day.
During the quarter, the Sangachal terminal exported around 47 million barrels of oil and condensate, which was sent mainly through the Baku-Tbilisi-Ceyhan (BTC) pipeline.
Gas is exported via the South Caucasus Pipeline (SCP), including the SCP expansion system and via Azerbaijan’s pipelines connecting the terminal’s gas processing facilities with Azerigas’s national grid system.
On average, around 74.4 million standard cubic metres (about 2,628 million standard cubic feet) of Shah Deniz gas was sent from the terminal daily during the first quarter of 2026.
Sangachal terminal electrification (STEL) project
During the first quarter of 2026, the Sangachal Terminal Electrification (STEL) project continued to make strong progress across construction activities both inside and outside the terminal fence line.
The new AzerEnerji substation located outside the fence line is now mainly complete, with overhead line installation fully completed. Within the terminal, execution has progressed in line with plan, with the overall critical path driven by the synchronous condenser, a key long-lead component. The first unit required to support the 2027 start-up is already on site.
The project is now firmly advancing through the main construction and installation phase, positioning the facility for commissioning readiness in the third quarter of 2026.
Construction activities are expected to be completed in two stages – Stage 1 in mid-2027, and Stage 2 by the end of 2028.
The $230 million STEL project will enable the terminal to connect with Azerbaijan’s national grid operated by AzerEnerji, via new facilities to be built both within and outside the terminal, including a new 220/110 kV electricity substation.
The STEL project is closely linked to the Shafag project, a 240MW AC solar plant being built in Jabrayil, via a new commercial structure called ‘virtual power transfer arrangement’. Based on this arrangement, the Shafag plant would produce power and deliver it to AzerEnerji in the Jabrayil district, while AzerEnerji would deliver an equivalent quantity of electricity to the Sangachal terminal near Baku. Together, the Shafag and STEL projects are expected to support the reduction of operational emissions by around 50% over the future life of the Sangachal terminal, based on the current outlook and plans.
The terminal currently uses seven gas turbines to generate the power it needs. Following the electrification, the turbines will be removed in phases, freeing up the fuel gas for export.
The shareholding interests in Shafag Jabrayil Solar Limited (SJSL) are: bp 40.01%, SOCAR Green 39.99%, Azerbaijan Business Development Fund 10%, and MVM 10%.
During the first quarter of 2026, construction activities for the Shafag project progressed at the site in the Jabrayil district. Procurement and delivery of key equipment, including photovoltaic modules, piles and structural components, were successfully completed, and significant progress was made on pile and tracker installation.
In early April, the project achieved a major milestone with the successful installation of the first solar panel at the site.
Local employment continued to increase, with around 350 people currently working on the project, including 123 individuals from the liberated areas. At peak construction, the project is expected to create more than 400 jobs, and existing camp facilities are being expanded to accommodate the growing workforce.
The project also maintained a strong focus on environmental protection, including close monitoring of vegetation clearance and ongoing coordination with the Ministry of Ecology and Natural Resources to support the safe relocation of wildlife.
Construction activities for the Shafag project are expected to continue through mid-2027.
In the first quarter of 2026, BTC Co. spent around $30 million in operating expenditure and $28 million in capital expenditure.
Since the 1,768 km BTC pipeline became operational in June 2006 till the end of the first quarter of 2026, it carried a total of more than 4.7 billion barrels (about 626 million tonnes) of crude oil loaded on 6,210 tankers and sent to world markets.
In the first quarter of 2026, about 49 million barrels (6 million tonnes) of BTC-exported crude oil was lifted at Ceyhan and loaded on 65 tankers.
The BTC pipeline currently carries mainly ACG crude oil and Shah Deniz condensate from Azerbaijan. In addition, other volumes of Caspian regional crude oil and condensate (Kazakhstan, Turkmenistan, other SOCAR volumes produced in Azerbaijan) continue to be transported via BTC.
In the first quarter of 2026, bp and its co-venturers spent around $785 million in operating expenditure and around $336 million in capital expenditure on Shah Deniz activities.
Production
During the quarter, the Shah Deniz field continued to provide gas to markets in Azerbaijan (to SOCAR), Georgia (to GOGC), Türkiye (to BOTAS), BTC in multiple locations and to buyers in Europe.
In the first quarter of 2026, the field produced around 7 billion standard cubic metres of gas and about 1 million tonnes (around 7 million barrels) of condensate in total from the Shah Deniz Alpha and Shah Deniz Bravo platforms.
The existing Shah Deniz facilities’ production capacity is currently about 74.2 million standard cubic metres of gas per day or approximately 27.1 billion standard cubic metres per year.
The Shah Deniz 2 project
In the first quarter of 2026, Shah Deniz 2 progressed with the subsea execution scope of the West flank wells.
While the Shah Deniz 2 activities, including the delivery of the remaining wells within the project, remain the primary mission for the subsea construction vessel Khankendi, during the first quarter the vessel was involved in a multi-well subsea intervention campaign in the ACG Deepwater Gunashli area supporting early identification of opportunities for pressure management and production rate enhancement of ACG. During this period, the diving support vessel Tofig Ismayilov provided life-of-field support, covering services, surveys, and interventions across all of the Shah Deniz 2 and ACG subsea producing assets.
This is part of the integrated schedule, ensuring the efficient utilization of the vessel and drilling rigs to optimize activities and accelerate well start-up dates.
Shah Deniz Compression (SDC) project
During the first quarter, the Shah Deniz Compression (SDC) project progressed safely and on schedule.
The SDC platform topsides and jacket fabrication activities moved forward as planned at the Bayil fabrication yard and the Heydar Aliyev Baku Deepwater Jackets Factory respectively, with steady progress on primary steel and structural components, including jacket elements and subsea structures.
Marine and subsea engineering activities are also on track, with the detailed design progressing as planned and key technical reviews completed.
Procurement continued to advance across several critical package streams, remaining aligned with fabrication and installation timelines.
The $2.9 billion SDC project is designed to help access and produce low pressure gas reserves in the field and maximize resources recovery. It is expected to enable around 50 billion cubic metres of additional gas and approximately 25 million barrels of additional condensate production and export from the field.
The project involves installation of a new compression facility – an electrically-powered unmanned compression platform, or Normally Unattended Installation (eNUI), and several associated facilities offshore in the Shah Deniz contract area. Additionally, it encompasses brownfield works to be undertaken at the Shah Deniz Alpha (SDA) and Bravo (SDB) platforms, as well as at the Sangachal terminal.
It is expected that the construction of the SDC platform will be completed in 2029 for the facility to be ready to receive first gas for compression from the SDA platform in 2029 and from the SDB platform in 2030.
Drilling
During the first quarter of 2026, the Shah Deniz Alpha platform completed additional perforation activities on the SDA09 and SDA07 wells.
The Shah Deniz 2 project progressed with the wells programme activities using the Istiglal and Heydar Aliyev rigs. During the quarter, the Istiglal rig carried out log and tieback run and subsequent completion activities on the SDD05 well on the West flank. The Heydar Aliyev rig continued drilling the SDH05 well on the East North flank.
In total, 23 wells have been drilled and completed for Shah Deniz 2 to date. These include five wells on the North flank, five wells on the West flank, four wells on the East South flank, five wells on the West South flank and four wells on the East North flank.
In the first quarter of 2026, the SCPC spent around $21 million in operating expenditure and $9 million in capital expenditure in total.
The SCP has been operational since late 2006, transporting Shah Deniz gas to Azerbaijan, Georgia and Türkiye. The expanded section of the pipeline commenced commercial deliveries to Türkiye in June 2018 and to Europe in December 2020.
During the quarter, the daily average export throughput of the SCP was 63.5 million cubic metres of gas per day.
Further evaluation of the Shafag-Asiman block is required to help identify the most suitable option to advance the project. To this end, work is underway to plan for future activities, including drilling a well into the Lower Surakhany reservoir. To enable these activities, the exploration period under the Shafag-Asiman Production Sharing Agreement (PSA) was extended in June 2025, with bp continuing as operator during this period.
The participating interests in Shafag-Asiman are as follows: bp (operator – 35%), SOCAR (35%), and TPAO (30%, joined the PSA in June 2025).
On the Karabagh field, an Ocean Bottom Node (OBN) seismic survey has been conducted to enhance the reservoir understanding, support well planning, and optimize field development strategies. The survey commenced in December 2025 and was completed ahead of schedule in mid-March 2026. Processing of the data acquired during the survey is currently ongoing.
Following this, work started in mid-March for a High-Resolution (HR) / Ultra-High Resolution (UHR) seismic survey to help identify geological hazards that could affect well integrity, as well as subsurface hazards that could impact the safe installation of a platform and other infrastructure. This survey is expected to last up to 45 days.
On the ADUA block, as a first step, a 2D HR seismic survey was conducted in April in water depths ranging from 20 to 40 metres, covering a small area located in the north-western part of the ADUA block. The primary objective of the survey was to acquire detailed subsurface data to a depth of approximately 1,500 metres to support the planning of future exploration wells. The survey will help identify shallow geological hazards, including faults, shallow gas accumulations, and other subsurface features that could pose risks to drilling operations and well integrity.
The EIA document for the ADUA seismic survey was disclosed for public consultations in December 2025, with the final document approved by the government in March this year.
At the end of the first quarter of 2026, the number of bp’s Azerbaijani national employees was 2,322 including fixed-term employees.
Since mid-2018, 90% of bp Azerbaijan’s professional staff has been nationals. Non-professional staff of bp in Azerbaijan is 100% nationalized.
bp will continue its efforts to optimize its learning and development programmes and will actively participate in public and private sector initiatives contributing to the development of the local talent market.
The success of projects in the Caspian region depends, in part, on the operators’ ability to create tangible benefits from these projects for the people of the region. To achieve this, bp and its co-venturers continue to implement major social investment projects, which include educational programmes, building skills and capabilities in local communities, improving access to social infrastructure in communities, supporting local enterprises through provision of access to finance and training, support for cultural legacy and sport, as well as technical assistance to public institutions.
In the first quarter of 2026, bp and its co-venturers in the bp-operated joint ventures spent about $0.2 million on social investment projects in Azerbaijan. During the quarter, this included 14 ongoing educational projects, two capacity-building and enterprise development programme and one environmental initiative.
In addition, in the first quarter, bp alone spent about $0.3 million on various social and sponsorship projects in Azerbaijan.
These included 16 ongoing educational initiatives, one capacity-building and enterprise development programmes, three projects promoting the country’s cultural heritage and sport, one environmental initiative, as well as five conferences and workshops on various themes – in total 26 projects.
For more information about bp and its co-venturers’ social investment projects please visit the bp Azerbaijan website at www.bp.com/azerbaijan.
Tamam Bayatly at bp’s press office in Baku.
Telephone: (+994 12) 525 58 95