1. Home
  2. Who we are
  3. Operations and projects
  4. Azeri-Chirag-Deepwater Gunashli
  5. Azeri Central East development project

Azeri Central East (ACE) development project

  • Next stage of development of giant ACG field in Caspian Sea;
  • New 100,000 barrel a day platform expected onstream;
  • New development approved in 25th year of landmark partnership

The $6 billion development includes a new offshore platform and facilities designed to process up to 100,000 barrels of oil per day. The project is expected to achieve first production in 2023 and produce up to 300 million barrels over its lifetime. 

 

The sanction is the first major investment decision by the ACG partnership since the extension of the ACG production sharing agreement (PSA) to 2049 was agreed in 2017. More than $36 billion has been invested into the development of the ACG area since the original PSA was signed in 1994. 

 

Construction activities, which commenced in July 2019 and run through mid-2022, will take place in-country utilizing local resources. It is expected that, at peak, construction activities will create up to 8,000 jobs.

 

The Azeri Central East (ACE) project is centred on a new 48-slot production, drilling and quarters platform located mid-way between the existing Central Azeri and East Azeri platforms in a water depth of approximately 140 metres. The project will also include new infield pipelines to transfer oil and gas from the ACE platform to the existing ACG Phase 2 oil and gas export pipelines for transportation to the onshore Sangachal Terminal. 

 

In addition, there will be a water injection pipeline installed between the East Azeri and ACE platforms to supply injection water from the Central Azeri compression and water injection platform to the ACE facilities.

 

In 2019, the project awarded the main fabrication, marine and subsea contracts and started construction activities in July. 

During the year, the Azeri Central East (ACE) project progressed according to the plan along with the other bp-operated activities.
 
The final major equipment packages were delivered to Baku at the end of the year completing the shipment of all equipment required for the project.
 
Fabrication activities on the topsides and drilling facilities continued at the fabrication yard in Bibi-Heybat. This included progressing the pipe erection and hydrotesting, cable pulling and testing. All modules of the living quarters were successfully installed on the topsides followed by the commencement of integration and internal hook-up activities. In addition, the upper deck panel was installed on the topsides, the helideck was lifted and installed on the living quarters. The topsides and the drilling module mechanical completion handovers progressed as planned. The drilling module commissioning at grade has already commenced and will continue in 2022 ahead of the jack and skid operation.
 
At the Heydar Aliyev Baku Deepwater Jackets factory (BDJF), the jacket fabrication continued with the final roll-up of the leg frames completed and assembly of the jacket towers commenced. The pipelay barge ‘Israfil Huseynov’ started the pipelay of the ACE oil and gas lines.

 

The  offshore installation works associated with the spare power scope on the East Azeri platform also progressed during the year.
 
At the end of the year, the ACE project reached the 65% progress milestone. The project construction activities are currently at peak and involve about 5,500 people across Baku, Europe and the UK, with the majority of them being Azerbaijani nationals.
 
All engineering, procurement and fabrication works remain on track to support first production from the ACE project in 2023.