South Caucasus pipeline

Read more about the pipeline exporting Azerbaijani gas to the world markets

The South Caucasus Pipeline (SCP) was built to export Shah Deniz gas from Azerbaijan to Georgia and Turkey. The pipeline starts from the Sangachal terminal near Baku. It follows the route of the Baku-Tbilisi-Ceyhan (BTC) crude oil pipeline through Azerbaijan and Georgia to Turkey, where it is linked to the Turkish gas distribution system. 

SCP was constructed jointly with BTC in order to minimise the environmental and social impact and to achieve capital and operating cost saving synergies.

South Caucasus Pipeline Company (SCPC)  has been responsible for the construction and operation of the whole pipeline. 

So SCP has a dual operatorship with BP as the technical operator being responsible for construction and operation of the SCP facilities and SOCAR Midstream Operations Limited, as commercial operator, is responsible for SCP's business administration. 

The pipeline has been operational since late 2006 transporting gas to Azerbaijan and Georgia, and starting from July 2007 to Turkey from Shah Deniz Stage 1.

The length of the pipeline is 691km, with 443 km in Azerbaijan and 248 km in Georgia. The  diameter  is a 42-inch . 

In 2015, SCP spent about $47.5 million in operating expenditure and about 1.1 billion in capital expenditure.

In 2015, SCP’s daily average throughput was 18.6 million cubic metres of gas per day. 

The SCP Co. shareholders are: BP, operator (28.8 per cent), AzSCP (10.0 per cent), TPAO (19 per cent), Petronas (15.5 per cent), Lukoil (10 per cent), NICO (10 per cent) and SGC Midstream (6.7 per cent).

SOUTH CAUCASUS PIPELINE EXPANSION

The expansion of the South Caucasus Pipeline is part of the Shah Deniz Full Field Development project. This expansion involves the laying of new pipeline across Azerbaijan and the construction of two new compressor stations in Georgia. This will triple the gas volumes exported through the pipeline to over 20 billion cubic metres per year.

At the border between Georgia and Turkey, the pipeline will link into other new pipelines to provide gas into Turkey and the European Union. 

A Final Investment Decision on the South Caucasus Pipeline Expansion (SCPX) project was taken on 17 December 2013, coincident with Shah Deniz Stage 2. 

In 2015, SCPX activities continued along the pipeline route across Azerbaijan and Georgia. 

In Azerbaijan, mainline construction continued to ramp up with approximately 71km of pipe welded. Trenching, lowering, laying and backfilling activities commenced at the end of November and are progressing. Stocks of pipe have been building up at the pipe yards along the route with more than 60% of the pipe needed for the Azerbaijan section already stored at Mugan, Kurdamir, Yevlakh, and Qazanchi pipe yards. The first horizontal directional drilling site at Agsu Canal has progressed well. 

In Georgia, main construction works have continued for Compressor Station 1 and have commenced for Compressor Station 2 and Area 81.  Pipe stringing has continued along the right of way with 27km in place and approximately 7km of pipe welded. Preparations for commencement of trenching, lowering and backfilling continued with the start of this activity expected in the first quarter of 2016.